Change the status of a work order and complete it.
Move a work order from scheduled to in progress, then mark it completed.
- 5 steps
- 3 min read
Part of the path for Service managersTechnicians
Before you start
Sign in with access to Work Orders. The work order must already exist. This example uses work order 1, Rooftop unit not cooling, for North Ridge Builders, which is already scheduled. Technician names are blurred in the pictures for privacy.
What is a work order status?
The status tells everyone where a job stands. A work order starts as NEW. It becomes SCHEDULED when it has a technician and a time. It is IN PROGRESS while the work is being done, and COMPLETED when the work is finished.
After COMPLETED there is one more step, FINALIZED. Finalizing locks the work order for good, so nobody can add time, expenses or edits. Office staff do it once the paperwork and the invoice are right. CANCELLED is for jobs that will not be done.
Completing is not the same as invoicing. Completed means the work on site is done. The invoice is made after that, from the same work order.
Open the work order
Click Work Orders in the menu on the left. Then click the work order in the list. The Status column shows where each job stands now.
Find the status button
Look under the customer name and the title. The coloured button shows the current status, here SCHEDULED. Click it to change the status.
Set it to In progress
A short list called Set status opens. Click In progress when the technician starts the job. The button turns orange and shows IN PROGRESS.
Set it to Completed
When the work is done, click the status button again and click Completed. PolarPath asks: Mark this work order as completed? Click OK.
Check the result
The status button is now green and shows COMPLETED. The work order moves to the Completed tile on the Work orders page.
The result.
The work order is COMPLETED. Regular users can no longer edit it. Supervisors still can. It is ready for the office to review, invoice and finalize.
If you get stuck
Finalized is grey in the list until the work order is completed. If PolarPath says to complete a checklist or an equipment inspection first, open the Checklists tab, finish it, then set the status again. If the status button itself is grey, the work order is finalized and locked. Picked the wrong status? Click the button and choose the right one, as long as the work order is not finalized.
What to do next
Create a work order
Write up a job for a customer so it can be scheduled and done.
6 simple steps →DispatchingSchedule a work order on the dispatch board
Give a waiting work order to a technician at a set time.
6 simple steps →Work ordersAssign a technician to a work order
Open a work order, choose its technician and add the customer PO number.
6 simple steps →