Track progress on the Gantt chart.

Record how much of an activity is done and colour bars so the team sees status at a glance.

  • 6 steps
  • 3 min read
Start step one

Part of the path for Project managers

Before you start

Sign in with access to Projects. The project must already have a schedule. This example uses the project North Ridge office retrofit for North Ridge Builders, with a sample schedule of three phases, eleven activities and two milestones. All names and dates are fictional.

Practice withNorth Ridge BuildersMaya ChenRooftop equipment replacement

What is progress tracking?

A Gantt chart is a calendar for a project. Each piece of work, called an activity, is drawn as a bar. The left end of the bar is the day the work starts and the right end is the day it ends, so you can see at a glance what happens when and what overlaps.

Each activity has a completion percent. 0% means not started and 100% means finished. When an activity is finished its bar turns green and striped with a check mark, and its name is crossed out in the list.

You can also give a bar its own colour, for example orange for work that needs attention.

01/06

Open the project

Click Projects in the menu on the left. Then click the project in the list.

02/06

Click Open schedule

On the project page, click Open schedule at the top. The Schedule page opens with the Gantt chart.

03/06

Open the activity

Click the activity name in the list, here Remove old rooftop unit. Its details open.

04/06

Set the completion

Under Completion, click a quick value such as 75%, or type the exact number. Click Completed at the top when the work is finished.

05/06

Choose a bar colour

Under Bar color, click a colour, here orange. Use default goes back to the normal blue.

06/06

Save and check the chart

Click Save activity. The bar shows the new colour. You can also tick the round box in front of a name in the list to mark it complete in one click.

The result.

The chart shows how far each activity has come and which ones are finished.

If you get stuck

Completed work cannot be undone by colour: untick the round box or set the completion back below 100% to reopen an activity. Phases show the progress of the activities inside them.

What to do next