Read the Gantt chart.

Understand the bars, phases, milestones and arrows, and zoom the calendar in and out.

  • 6 steps
  • 3 min read
Start step one

Part of the path for Project managers

Before you start

Sign in with access to Projects. The project must already have a schedule. This example uses the project North Ridge office retrofit for North Ridge Builders, with a sample schedule of three phases, eleven activities and two milestones. All names and dates are fictional.

Practice withNorth Ridge BuildersMaya ChenRooftop equipment replacement

What is the Gantt chart?

A Gantt chart is a calendar for a project. Each piece of work, called an activity, is drawn as a bar. The left end of the bar is the day the work starts and the right end is the day it ends, so you can see at a glance what happens when and what overlaps.

Blue bars are activities. Green striped bars with a check are finished. Dark bars are phases, also called summaries, which group several activities. A black diamond is a milestone, a single important day such as Handover to customer. Thin arrows are dependencies: the arrow goes from the work that must finish first to the work that waits for it.

The purple line is today. Anything to its left should already be done.

01/06

Open the project

Click Projects in the menu on the left. Then click the project in the list.

02/06

Click Open schedule

On the project page, click Open schedule at the top. The Schedule page opens with the Gantt chart.

03/06

Read the two halves

On the left is the list of activities with their Start and End dates. On the right is the calendar with a bar for each activity. The legend under the chart explains the colours: Task, Completed, Critical, Summary, Milestone and Baseline.

04/06

Zoom in and out

Use Day, Week, Month, Quarter and Year to change how much time fits on the screen. Week shows each day. Click Today to scroll the calendar back to the current date.

05/06

Jump to a period

Click Date range to pick a quick range: Next 14 days, Next 30 days or Next 90 days. Clear date filter shows the whole schedule again.

06/06

See the big picture

Click Roadmap. The Roadmap overview shows only the phases, each as one bar with the number of activities in it. It is a short view for the customer or the boss. Click Timeline to go back.

The result.

You can read who does what and when, see which work is finished, and move the calendar to any period.

If you get stuck

If the chart is empty, the project has no activities yet: follow Add activities and milestones. If bars are cut off at the right, scroll the calendar sideways or choose a larger zoom such as Quarter.

What to do next