Add an item to the deficiency list.

Record something that still has to be fixed before the job is handed over.

  • 6 steps
  • 3 min read
Start step one

Part of the path for Project managers

Before you start

Sign in with access to Projects. The project must already exist. This example uses the project North Ridge office retrofit for North Ridge Builders. All names and details are fictional.

Practice withNorth Ridge BuildersMaya ChenRooftop equipment replacement

What is a deficiency list?

A deficiency list is the list of small things that are not right yet near the end of a job: a missing ceiling tile, a scratched panel, a label that was forgotten. Many people call it a punch list.

Each item says where the problem is, what it is, which trade has to fix it and how urgent it is. When every item is completed, the job is ready to hand over.

A deficiency is different from an issue. An issue is a problem during the job. A deficiency is unfinished or faulty work found at the end. You can print the whole list as a PDF for the customer or a subcontractor.

01/06

Open the project

Click Projects in the menu on the left. Then click the project in the list.

02/06

Open the Deficiency List tab

On the project page, click the Deficiency List tab. Then click Add deficiency.

03/06

Choose Add single item

A short menu opens. Click Add single item. Start walkthrough is for walking the site and adding many items in a row, and Import from Excel brings in a spreadsheet.

04/06

Say where and what

In Location, write where the problem is, for example: Level 2, meeting room 204. In Description, write what is wrong. You can add a photo instead of a description.

05/06

Add the trade and the priority

In Trade, write who has to fix it, here Ceilings. Leave Priority as Medium or change it. Assignee, Vendor and Due date are optional.

06/06

Save and check the list

Click Save deficiency. The item shows in the list as DEF-001 under its location, with the status OPEN. Print Deficiency List makes a PDF of the whole list.

The result.

The item is on the deficiency list of the project with the status OPEN. Click Complete on its line when the work is fixed.

If you get stuck

Save deficiency needs a Location and either a Description or a photo. If Add deficiency is grey, the list is closed: use New list to start another one. Internal notes stay inside your company and are left out of the printed PDF.

What to do next