Record a change on a project.

Write down extra or changed work, with its price and the days it adds.

  • 5 steps
  • 3 min read
Start step one

Part of the path for Project managers

Before you start

Sign in with access to Projects. The project must already exist and be active. This example uses the project North Ridge office retrofit for North Ridge Builders. All names and amounts are fictional.

Practice withNorth Ridge BuildersMaya ChenRooftop equipment replacement

What is a change?

A change is work that was not in the original agreement. The customer asks for something extra, something is removed, or site conditions force a different way of doing the job. A change usually alters the price, the end date or both.

In PolarPath every change starts as a change request. It shows with a COR number, for example COR-00001, and the status DRAFT. COR means change order request. Once the customer approves it, it becomes a change order and gets its official CO number.

Recording changes matters because the project price is the contract plus all approved changes. If a change is not written down and approved, you may do the work and not get paid for it.

A change is different from an RFI. An RFI is only a question. A change is an agreement about money and time.

01/05

Open the project

Click Projects in the menu on the left. Then click the project in the list.

02/05

Open Changes and start a new one

On the project page, click the Changes tab. Then click New Change on the right.

03/05

Say what changed and why

In What changed?, write a short line, for example: Add a second rooftop unit. In Why did it change?, give the reason in a sentence. The reason helps the customer approve it faster.

04/05

Add the days and the price

Under Price and time impact, enter how many days the change adds in Added days, here 5. Enter what the customer will pay for it in Price, here 8500. You can also pick a date in Approval needed by.

05/05

Create the change

Click Create change. The change appears in the Changes list as COR-00001 with the status DRAFT and a revenue of $8,500.00.

The result.

The change is saved on the project as a draft change request. It is counted under Awaiting approval. The project price does not go up until the customer approves the change.

If you get stuck

If Create change does nothing, fill in What changed?: it is the only field you must fill. Leave Price empty if the change costs the customer nothing. Under Link to existing work you can tie the change to an Issue, an RFI or a Task or activity so the history stays together. To send the change to the customer for approval, open it from the list.