Add activities, milestones and links.

Build the schedule: add an activity, choose its type and tie it to the work that must finish first.

  • 6 steps
  • 3 min read
Start step one

Part of the path for Project managers

Before you start

Sign in with access to Projects. The project must already have a schedule. This example uses the project North Ridge office retrofit for North Ridge Builders, with a sample schedule of three phases, eleven activities and two milestones. All names and dates are fictional.

Practice withNorth Ridge BuildersMaya ChenRooftop equipment replacement

What goes into a schedule?

A Gantt chart is a calendar for a project. Each piece of work, called an activity, is drawn as a bar. The left end of the bar is the day the work starts and the right end is the day it ends, so you can see at a glance what happens when and what overlaps.

There are three types. A Task is a piece of work with a start and an end. A Summary is a phase that groups tasks, such as Preparation or Installation. A Milestone is one important day with no length, such as Crane permit approved.

A link, or dependency, says one activity must wait for another. The usual kind is Finish to Start: the second activity can start only after the first one is finished. Other kinds are Start to Start, Finish to Finish and Start to Finish.

01/06

Open the project

Click Projects in the menu on the left. Then click the project in the list.

02/06

Click Open schedule

On the project page, click Open schedule at the top. The Schedule page opens with the Gantt chart.

03/06

Click New activity

On the Schedule page, click New activity at the top right. The Add activity form opens.

04/06

Name it and choose the type

In Name, write what the activity is, for example: Crane permit approved. In Type, choose Task, Summary or Milestone. Here we choose Milestone.

05/06

Link it to earlier work

In Related activity, choose the activity that must happen first, here Order rooftop unit and curb adapter. Leave Relationship type as Finish to Start unless the work overlaps.

06/06

Set the date and create it

Pick the Milestone date, or for a task the start and end dates under Schedule. Click Create activity. The new line appears in the list and on the calendar, here as a black diamond.

The result.

The activity is part of the schedule, with its type, its dates and its link to the work before it.

If you get stuck

Name is the only field you must fill. The form does not move the date for you to match the linked activity: check that the date comes after the work it waits for. You can also drag the round plus at the end of a bar onto another bar to link two activities.

What to do next