Add activities, milestones and links.
Build the schedule: add an activity, choose its type and tie it to the work that must finish first.
- 6 steps
- 3 min read
Part of the path for Project managers
Before you start
Sign in with access to Projects. The project must already have a schedule. This example uses the project North Ridge office retrofit for North Ridge Builders, with a sample schedule of three phases, eleven activities and two milestones. All names and dates are fictional.
What goes into a schedule?
A Gantt chart is a calendar for a project. Each piece of work, called an activity, is drawn as a bar. The left end of the bar is the day the work starts and the right end is the day it ends, so you can see at a glance what happens when and what overlaps.
There are three types. A Task is a piece of work with a start and an end. A Summary is a phase that groups tasks, such as Preparation or Installation. A Milestone is one important day with no length, such as Crane permit approved.
A link, or dependency, says one activity must wait for another. The usual kind is Finish to Start: the second activity can start only after the first one is finished. Other kinds are Start to Start, Finish to Finish and Start to Finish.
Open the project
Click Projects in the menu on the left. Then click the project in the list.
Click Open schedule
On the project page, click Open schedule at the top. The Schedule page opens with the Gantt chart.
Click New activity
On the Schedule page, click New activity at the top right. The Add activity form opens.
Name it and choose the type
In Name, write what the activity is, for example: Crane permit approved. In Type, choose Task, Summary or Milestone. Here we choose Milestone.
Link it to earlier work
In Related activity, choose the activity that must happen first, here Order rooftop unit and curb adapter. Leave Relationship type as Finish to Start unless the work overlaps.
Set the date and create it
Pick the Milestone date, or for a task the start and end dates under Schedule. Click Create activity. The new line appears in the list and on the calendar, here as a black diamond.
The result.
The activity is part of the schedule, with its type, its dates and its link to the work before it.
If you get stuck
Name is the only field you must fill. The form does not move the date for you to match the linked activity: check that the date comes after the work it waits for. You can also drag the round plus at the end of a bar onto another bar to link two activities.
What to do next
Read the Gantt chart
Understand the bars, phases, milestones and arrows, and zoom the calendar in and out.
6 simple steps →Gantt chartsChange the dates of an activity
Move an activity or make it longer or shorter when the plan changes.
5 simple steps →Gantt chartsTrack progress on the Gantt chart
Record how much of an activity is done and colour bars so the team sees status at a glance.
6 simple steps →