Record a change on a project.
Write down extra or changed work, with its price and the days it adds.
- 5 steps
- 3 min read
Part of the path for Project managers
Before you start
Sign in with access to Projects. The project must already exist and be active. This example uses the project North Ridge office retrofit for North Ridge Builders. All names and amounts are fictional.
What is a change?
A change is work that was not in the original agreement. The customer asks for something extra, something is removed, or site conditions force a different way of doing the job. A change usually alters the price, the end date or both.
In PolarPath every change starts as a change request. It shows with a COR number, for example COR-00001, and the status DRAFT. COR means change order request. Once the customer approves it, it becomes a change order and gets its official CO number.
Recording changes matters because the project price is the contract plus all approved changes. If a change is not written down and approved, you may do the work and not get paid for it.
A change is different from an RFI. An RFI is only a question. A change is an agreement about money and time.
Open the project
Click Projects in the menu on the left. Then click the project in the list.
Open Changes and start a new one
On the project page, click the Changes tab. Then click New Change on the right.
Say what changed and why
In What changed?, write a short line, for example: Add a second rooftop unit. In Why did it change?, give the reason in a sentence. The reason helps the customer approve it faster.
Add the days and the price
Under Price and time impact, enter how many days the change adds in Added days, here 5. Enter what the customer will pay for it in Price, here 8500. You can also pick a date in Approval needed by.
Create the change
Click Create change. The change appears in the Changes list as COR-00001 with the status DRAFT and a revenue of $8,500.00.
The result.
The change is saved on the project as a draft change request. It is counted under Awaiting approval. The project price does not go up until the customer approves the change.
If you get stuck
If Create change does nothing, fill in What changed?: it is the only field you must fill. Leave Price empty if the change costs the customer nothing. Under Link to existing work you can tie the change to an Issue, an RFI or a Task or activity so the history stays together. To send the change to the customer for approval, open it from the list.
What to do next
Start a project and find your way around it
Open Projects, start a new project from a won quote and learn the tabs of the project page.
5 simple steps →RFIsCreate an RFI on a project
Write down a question for the customer or the designer and track the answer.
6 simple steps →Gantt chartsAdd activities, milestones and links
Build the schedule: add an activity, choose its type and tie it to the work that must finish first.
6 simple steps →