Save a baseline and compare the plan.

Freeze a copy of the schedule so you can see later what moved.

  • 6 steps
  • 3 min read
Start step one

Part of the path for Project managers

Before you start

Sign in with access to Projects. The project must already have a schedule. This example uses the project North Ridge office retrofit for North Ridge Builders, with a sample schedule of three phases, eleven activities and two milestones. All names and dates are fictional.

Practice withNorth Ridge BuildersMaya ChenRooftop equipment replacement

What is a baseline?

A Gantt chart is a calendar for a project. Each piece of work, called an activity, is drawn as a bar. The left end of the bar is the day the work starts and the right end is the day it ends, so you can see at a glance what happens when and what overlaps.

A baseline is a saved copy of the schedule at one moment, usually when the customer approves the plan. Later, PolarPath can draw the baseline as thin grey bars under the real bars, so you see at once which activities slipped and by how much.

Save a new baseline only when the customer agrees to a new plan. Keep the old ones to show the history.

01/06

Open the project

Click Projects in the menu on the left. Then click the project in the list.

02/06

Click Open schedule

On the project page, click Open schedule at the top. The Schedule page opens with the Gantt chart.

03/06

Click Baseline

On the Schedule page, click Baseline at the top.

04/06

Save the current schedule

Click Save current schedule as baseline. PolarPath asks for a name. Type one, for example Plan at start, and click OK.

05/06

Check the message

A message says Baseline saved. The comparison is now switched on.

06/06

Compare later

Open Baseline again. Under Compare to you see each saved baseline, here Plan at start. Show comparison bars or Hide comparison bars turns the grey bars on or off. Clear comparison stops comparing.

The result.

The plan is saved and you can compare the current schedule with it at any time.