Change the dates of an activity.
Move an activity or make it longer or shorter when the plan changes.
- 5 steps
- 3 min read
Part of the path for Project managers
Before you start
Sign in with access to Projects. The project must already have a schedule. This example uses the project North Ridge office retrofit for North Ridge Builders, with a sample schedule of three phases, eleven activities and two milestones. All names and dates are fictional.
Why change the dates?
A Gantt chart is a calendar for a project. Each piece of work, called an activity, is drawn as a bar. The left end of the bar is the day the work starts and the right end is the day it ends, so you can see at a glance what happens when and what overlaps.
Plans change: a delivery is late, a crew finishes early. Keeping the dates up to date means the schedule you show the customer is the real one.
When you move an activity, the activities linked after it may need to move too. Check the arrows after every change.
Open the project
Click Projects in the menu on the left. Then click the project in the list.
Click Open schedule
On the project page, click Open schedule at the top. The Schedule page opens with the Gantt chart.
Open the activity and click Edit activity
Click the activity name in the list. Its details open. Scroll down and click Edit activity.
Pick the new dates
Click the dates under Schedule. In the calendar, click the new first day, then the new last day. Here the walkthrough moves to December 9 to December 10.
Save the change
Click Save changes. The Start and End columns and the bar on the calendar move to the new dates.
The result.
The activity sits on its new dates in the list and on the calendar.
If you get stuck
You can also drag a bar sideways on the calendar to move it, or drag its right edge to make it longer. If a linked activity now starts before the one it waits for, move it too.
What to do next
Add activities, milestones and links
Build the schedule: add an activity, choose its type and tie it to the work that must finish first.
6 simple steps →Gantt chartsSave a baseline and compare the plan
Freeze a copy of the schedule so you can see later what moved.
6 simple steps →Gantt chartsRead the Gantt chart
Understand the bars, phases, milestones and arrows, and zoom the calendar in and out.
6 simple steps →